November 2003

An update of the progress of work on
PC-744 Program Management Contract

Featuring George Karmo, P.E.
Senior Vice President

“Time passes when one is having fun!” commented George Karmo as the PC-744 program for rehabilitation of the Detroit Wastewater Treatment Plant moved into its fourth year. During the first three years of the five year term program, the Detroit Wastewater Partners (DWP), a joint venture of Sverdrup and Wade-Trim in association with Tucker, Young, Jackson, Tull, Inc (TYJT) and twelve (12) other sub-consultants has initiated delivery and made substantial progress for fifty (50) capital improvement projects from project definition phase through design and construction, conducting annual needs assessments of the wastewater treatment plant, and providing operation and maintenance (O&M) support services. Some of these plant-critical projects included new centrifuge dewatering facilities in Complex I, Central Off-Load Facility, Pumping Station No. 1 rehabilitation, Aerations Deck rehabilitation, and Sludge Complexes A and B rehabilitation.


George Karmo, P.E.
Senior Vice President


The value of actual planning and design, construction, and operation and maintenance support started to-date is approximately $200,000,000 out of a projected $281,000,000 (not including the contract optional work). This means that 71% of the base contract value has been already expended and/or committed.

As the major team sub-consultant, TYJT’s staff has and continues to perform activities in planning and engineering, procurement, project management, construction management, and O&M services. “We have currently a total of twelve (12) full-time staff members located at DWP’s site office assisted by approximately ten (10) staff members working part-time at the TYJT and DWP offices” reports Mr. Karmo.


DWP-2001 (PC-75) Complex II Lower Level DeWatering Improvements (prime consultant for design TYJT)


As DWP’s Procurement Manager, George Karmo has led the Program’s efforts for procurement. The procurement activities involved two rounds of pre-qualification for design consultants; two rounds of pre-qualification for job order contractors; procurement of design consultants for twenty four (24) projects; design/build teams for eight (8) projects; job order contractors for seven (7) projects; and general construction contractors for eight (8) construction projects. Other TYJT staff providing services for PC-744 include Satish Madan for needs assessment, planning and engineering, and project management; Andre Hindo for project management; Tony Wachocki, Bill Hansen and Louise Bacon for O&M liaison and services; Jeff Mitsopoulos, Eric Tucker, Mohammed Chammaa, Mukesh Bhatt, Jim Casha, Ed Zajdel, and Zane Marougy for construction management services. Other TYJT support staff include Bhagu Patel for procurement and asset management; Peck Wee and Donald Stickel for planning and engineering; Larry O’Brien for local economic development; and Pat Yeargin, Coretta Richardson and Megan Snethkamp for procurement administrative activities.

TYJT site and home-office staff has demonstrated outstanding skills and commitment to the Program. “TYJT continues to be recognized by DWP management for our outstanding performance” reports Mr. Karmo.


DWP-1074, Design/Build, Central Off-load Facility

DWP-1007, Pumping Stations No. 1 Rehabilitation
Andre Hindo - Senior Engineer

DWP-1021, Parking Structure Rehabilitation

SPOTLIGHT

Grant Hilbers, P.E.

When I started at Tucker-Young I came with four years of experience, a Masters and a P.E. (Technically my Michigan P.E. license was in the mail at the time) I completed my Masters full time, immediately after I finished my Bachelors. While completing my Masters I was both a teaching assistant and research assistant. Once I completed my Masters I decided I had more than enough schooling.


One of my initial assignments was to complete some piping layout on a couple of drawings for Don McHarness for DWSD contract PC-750. Since that initial assignment my involvement with PC-750 has increased to the point that I have been responsible for coordinating a large portion of the project for the past year and a half, while construction has been underway.

PC-750 involves the replacement of belt filter presses with new sludge dewatering equipment at the Detroit Wastewater Treatment Plant with a construction cost of approximately $19 million dollars. Tucker, Young is the prime consulting firm leading a team of four companies. Among our sub consultants is Metcalf and Eddy, a well known national firm with an expertise in wastewater treatment.

My involvement in coordinating the engineering services during construction has been a challenging and rewarding experience. Dealing with the construction manger, the engineering team and the clients' representatives has lead to many stress filled days over the past few years. But you won't hear me ask anyone to take the project away though, because I know there are engineers with much more experience than me that would love to be in my position.

Assignments to work on projects of this size do not come often, especially for young engineers. One of the clear advantages of working at Tucker, Young is the opportunity to work on this type of interesting project. I simply would not have had this kind of opportunity working at a national firm.

Currently I am working on five projects of various sizes, including some work on the Long Term CSO Control Project in Toledo. The Toledo experience has been interesting. Establishing an office in Toledo will be an up hill battle since Tucker, Young, Jackson, Tull, Inc. does not have the benefit of the reputation in that area as we do in the Detroit market. I am confident that once we land a few more jobs that our reputation as a capable engineering firm will open the door to some of the larger projects that are planned by the City over the next ten years.


PC-750 Photos
To Contact Us
© 2003 Tucker, Young, Jackson, Tull, Inc. All rights reserved.